Diadon Enterprises © 2018

Minneapolis light rail extension $9.5M over budget, 9 years behind schedule | Dump Trucks Charlotte NC

Rendering of a grey metro station with a red roof against a blue sky.
Rendering of the Golden Triangle station in Eden Prairie, part of the Southwest Corridor light rail extension project. Courtesy of Metropolitan Council

Columbus Ohio Dump Truck Company Brief:

  • The $2.74 billion Southwest Corridor light rail project between Minneapolis and its southwestern suburbs has more than doubled in cost and is nine years behind schedule, a new report from the Minnesota Office of the Legislative Auditor found. The audit identifies the main factors that delayed the extension and drove up the price.
  • A Lunda/McCrossan joint venture began construction on the extension in 2019. The project entails building 16 new transit stations, two light rail tunnels and a 14.5-mile light rail track. The 2011 estimate for the columbus oh dump truck company was $1.25 billion.
  • As a result of the ensuing cost increases, about $535 million of its budget is unfunded and no funding source has yet been identified, according to the audit. The rest of the additional costs are being paid for with federal, state and local funding.

Dump Trucks Columbus OH Insight:

The Southwest Corridor light rail project has encountered numerous delays and cost overruns both before and after construction started in 2019. In response to these challenges, in March 2022 the Minnesota Legislature directed its auditor to review the project. The report identified three factors as key drivers of delays and cost increases:

  • Uncertainty about the final location of freight rail along the project’s alignment. This proximity resulted in costly scope and design changes as well as schedule delays.
  • The need for a concrete barrier wall between freight rail and light rail traffic along a portion of the alignment.
  • The construction of a light rail tunnel in Minneapolis’s Kenilworth Corridor. The contractor had trouble pressing the sheet piles into the soil and the process ultimately took twice as long as anticipated.

The Metropolitan Council is the lead public agency on the project, and is working with federal, state, county and local agencies to execute it. As of April 29, the Council had approved 622 change orders that amounted to a net cost of $225 million, the report found, including construction of the previously deferred Eden Prairie station, the longer concrete barrier and the tunnel through the Kenilworth Corridor.

The audit was limited in scope, however. It did not evaluate whether the cost overruns or project delays were justified, nor did it evaluate the quality of project designs and engineering or whether different design choices could have resulted in less expense or fewer delays. 

The extension was initially supposed to open by 2018. That opening date has now been pushed to 2027.

The extension’s design and engineering contractor, AECOM Technical Services, started to raise concerns about quality of construction, cost of change columbus oh dump truck company orders and other elements in 2019, according to an October auditor’s letter in response to two Minneapolis lawmakers who requested that it review the Southwest project.

“There has been a prolonged and significant difference of opinion between representatives of the Metropolitan Council and [AECOM] regarding the preparation of independent cost estimates on the Southwest LRT project, as well as other project issues,” the auditor’s letter reads. “We have not examined the validity of [AECOM’s] allegations or the Council’s responses.”

A program evaluation scheduled for release in early 2023 will explore additional aspects of the problems with the Southwest extension project

Construction Dive news delivered to your inbox

Get the free daily newsletter read by industry experts

  • view sample
  • view sample

Editors' picks