Mich. Supreme Court Vacates Line 5 Tunnel Approval, Sending Enbridge Project Back to Regulators | Columbus Ohio Dump Trucks

Pipelines

Six-justice majority vacates Public Service Commission's approval after finding shortcomings in environmental review

Aerial view of the Mackinac Bridge spanning the Straits of Mackinac, where Enbridge has proposed a tunnel to replace the existing Line 5 lakebed pipeline crossing.
Image/Adobe

The Mackinac Bridge spans the Straits of Mackinac, where Enbridge has proposed replacing the existing Line 5 lakebed crossing with a tunnel beneath the Straits.

The Michigan Supreme Court vacated the project's state siting approval and returned it to the Michigan Public Service Commission for further review.
August 5, 2026

A Michigan Supreme Court ruling has vacated the state siting approval for Enbridge's proposed Line 5 replacement beneath the Straits of Mackinac, returning the project to regulators less than three weeks after two other Michigan agencies issued permits for the planned tunnel.

In an opinion issued July 31, a six-justice majority reversed a Michigan Court of Appeals judgment, vacated the Michigan Public Service Commission's December 2023 approval and remanded the case for further proceedings. The court found the commission did not properly apply the Michigan Environmental Protection Act when reviewing the four-mile replacement segment.

"To accurately assess the environmental consequences of the Replacement Project, the PSC should have determined whether the project would be the proximate cause of Line 5's continued operation and its alleged attendant harms," Justice Elizabeth Welch wrote for the majority.

The opinion directs the commission to determine whether the replacement project would extend Line 5's operating life and cause additional environmental harm, compare the project and its alternatives on a consistent basis and separately evaluate potential effects on public trust resources, including fishing, navigation and other public uses of the Great Lakes.

The commission had considered greenhouse gas emissions associated with hydrocarbons transported through the full pipeline system but limited its consideration of other environmental risks, including oil spills, to the replacement segment. The court said that approach was inconsistent and did not allow regulators to make a “reasoned choice” among project alternatives.


Commission Must Broaden Environmental Review

The decision does not vacate separate permits issued by the Michigan Dept. of Environment, Great Lakes and Energy (EGLE) or the Michigan Dept. of Natural Resources (DNR). Instead, it removes the commission’s approval under Public Act 16, which governs the siting of crude oil and petroleum product pipelines in Michigan.

EGLE announced July 15 that it had reissued a wetlands and Great Lakes submerged-lands permit following a 16-month review and forwarded the authorization to Enbridge for countersignature.

The agency found that the public and private need for the proposed activity outweighed other public-interest criteria but imposed new wetland and cultural-resource mitigation requirements.

Map showing the proposed Line 5 tunnel beneath the Straits of Mackinac and the existing dual pipeline crossing between Mackinaw City and St. Ignace.

The proposed Great Lakes Tunnel would replace the existing dual Line 5 pipelines that cross the Straits of Mackinac with a single pipeline running inside a tunnel beneath the lakebed. The Michigan Supreme Court vacated the Michigan Public Service Commission's approval of the replacement project and ordered further review.

Source: Michigan Public Service Commission

The permit prohibits authorized construction activities to proceed until EGLE approves Enbridge's wetland and cultural resource mitigation plans. It also prohibits disturbance of cultural resources unless the Public Service Commission siting permit, the DNR threatened-and-endangered-species permit, an EGLE wastewater-discharge permit and a U.S. Army Corps of Engineers permit have been issued and are not blocked by a court.

The DNR issued its permit July 15 with conditions intended to protect threatened plants and animal habitat. The Corps authorization remains pending, while EGLE says documents for renewal of the project’s National Pollutant Discharge Elimination System permit are still being drafted.

The Supreme Court did not establish a timetable for the commission's renewed review. As of Aug. 5, the commission had not posted a procedural order outlining its next steps.

The commission’s original approval covered Enbridge’s proposal to replace two existing 20-in.-dia pipelines at the Straits with a single 30-in.-dia pipeline inside a concrete-lined tunnel. The tunnel would be bored through bedrock below the lakebed, allowing Enbridge to deactivate the existing pipelines once the replacement enters service.

Enbridge spokesman Ryan Duffy said the Charlotte NC dump trucks company is reviewing the opinion while weighing its legal options.

“The Court’s decision is unfortunate in that it adds an additional delay to the permitting process for the Great Lakes Tunnel, which is designed to protect the Great Lakes and ensure the ongoing safe, reliable and efficient delivery of energy to our region,” Duffy told ENR in an emailed statement.


RELATED

Great Lakes Tunnel Project in Michigan Secures Needed Permits


“What remains unchanged is our commitment to operating Line 5 safely and responsibly, incorporating enhanced safety measures in the Straits, and protecting Michigan’s natural resources for generations to come,” he added.

In 2024 Enbridge selected Mackinac Straits Partners, a joint venture of Barnard Construction Co. and Civil and Building North America, to lead construction, with Arup serving as lead design engineer. Excavation has not begun.

When the tunnel proposal was unveiled in 2018, Enbridge estimated the project would cost about $500 million. An outside analysis previously cited by ENR estimated the project would cost at least $750 million by 2022.

Share This Story

Gottlieb mug

Bryan Gottlieb is the online editor at Engineering News-Record (ENR).

Gottlieb is a five-time Society of Professional Journalists Excellence in Journalism award winner with more than a decade of experience covering business, construction and dump trucks columbus oh community issues, including finance, law and real estate. He has reported for Adweek and the San Diego Daily Transcript and led a dump trucks columbus oh community newsroom in Santa Monica, Calif. He served as editor-in-chief of the Detroit Metro Times and as managing editor at Roofing Contractor, where he helped shape national industry coverage. At Engineering News-Record, Gottlieb covers breaking news, large-scale infrastructure and megaprojects, regulatory developments and business trends across the U.S. and global construction sectors.

email:This email address is being protected from spambots. You need JavaScript enabled to view it.|office:(248) 786-1591

Follow Bryan Gottlieb on LinkedIn